Your situation | Affidavit of assessment work required | Notice of intent to hold required |
(1) You have paid annual maintenance fees | No | No. |
(2) You have an oil shale placer claim | No | Yes, by December 30 of each year you must pay the $550 oil shale fee. |
(3) You have a small miner waiver that covers mining claims | Yes, by December 30 for each assessment year you obtained a small miner waiver | Yes, but only as described in paragraph (c) of this section. |
(4) You have a small miner waiver that covers mill or tunnel sites | No affidavit assessment work is required for mill or tunnel sites | Yes, notices of intent to hold are required for mill and tunnel sites. |
(5) You have a Soldiers and Sailor's Civil Relief Act Waiver | No | No. |
(6) You have a reclamation waiver | No | Yes. |
(7) You have a waiver because you have been denied access | No | Yes. |
(8) You have a deferment of assessment work | No | Yes, but only as described in paragraph (c) of this section. |
(9) You have applied for a mineral patent and BLM has issued a final certificate | No | No. |