Current through September 30, 2024
Section 3602.27 - When will BLM extend the term of a contract?BLM may grant a one-time extension of the contract not to exceed 1 year, if:
(a)(1) For contracts with terms over 90 days, BLM receives your written request between 30 and 90 days before the contract expires; or(2) For contracts with terms of 90 days or less, BLM receives your written request not later than 15 days before the contract expires; and(b) You show in writing that the delay in removing the mineral materials was due to causes beyond your control and was not due to your fault or negligence.