Before constructing pipelines and well field facilities on Federal lands leased for geothermal resources, you as lessee, unit operator, or facility operator must submit to BLM a utilization plan and facility construction permit addressing any pipelines or facilities. Do not start construction of your pipelines or facilities until BLM approves your facility construction permit.
43 C.F.R. § 3271.13