Current through September 30, 2024
Section 3162.3-1 - Drilling applications and plans(a) Each well shall be drilled in conformity with an acceptable well-spacing program at a surveyed well location approved or prescribed by the authorized officer after appropriate environmental and technical reviews (see § 3162.5-1 of this title). An acceptable well-spacing program may be either (1) one which conforms with a spacing order or field rule issued by a State Commission or Board and accepted by the authorized officer, or(2) one which is located on a lease committed to a communitized or unitized tract at a location approved by the authorized officer, or(3) any other program established by the authorized officer.(b) Any well drilled on restricted Indian land shall be subject to the location restrictions specified in the lease and/or Title 25 of the CFR.(c) The operator shall submit to the authorized officer for approval an Application for Permit to Drill for each well. No drilling operations, nor surface disturbance preliminary thereto, may be commenced prior to the authorized officer's approval of the permit.(d) The Application for Permit to Drill process must be initiated at least 30 days before commencement of operations is desired. Prior to approval, the application must be administratively and technically complete. A complete application consists of Form 3160-3 and the following attachments: (1) A drilling plan, which may already be on file, containing information required by paragraph (e) of this section and appropriate orders and notices.(2) A surface use plan of operations containing information required by paragraph (f) of this section and appropriate orders and notices.(3) Evidence of bond coverage as required by the Department of the Interior regulations.(4) For an oil well, a Waste Minimization Plan (WMP), as required by paragraph (j) or a self-certification statement, as required by paragraph (k) (These requirements do not apply to gas wells); and(5) Such other information as may be required by applicable orders and notices.(e) Each drilling plan shall contain the information specified in applicable notices or orders, including a description of the drilling program, the surface and projected completion zone location, pertinent geologic data, expected hazards, and proposed mitigation measures to address such hazards. A drilling plan may be submitted for a single well or for several wells proposed to be drilled to the same zone within a field or area of geological and environmental similarity. A drilling plan may be modified from time to time as circumstances may warrant, with the approval of the authorized officer.(f) The surface use plan of operations shall contain information specified in applicable orders or notices, including the road and drillpad location, details of pad construction, methods for containment and disposal of waste material, plans for reclamation of the surface, and other pertinent data as the authorized officer may require. A surface use plan of operations may be submitted for a single well or for several wells proposed to be drilled in an area of environmental similarity.(g) For Federal lands, upon receipt of the Application for Permit to Drill or Notice of Staking, the authorized officer shall post the following information for public inspection at least 30 days before action to approve the Application for Permit to Drill: the company/operator name; the well name/number; the well location described to the nearest quarter-quarter section (40 acres), or similar land description in the case of lands described by metes and bounds, or maps showing the affected lands and the location of all tracts to be leased and of all leases already issued in the general area; and any substantial modifications to the lease terms. Where the inclusion of maps in such posting is not practicable, maps of the affected lands shall be made available to the public for review. This information also shall be provided promptly by the authorized officer to the appropriate office of the Federal surface management agency, for lands the surface of which is not under Bureau jurisdiction, requesting such agency to post the proposed action for public inspection for at least 30 days. The posting shall be in the office of the authorized officer and in the appropriate surface managing agency if other than the Bureau. The posting of an Application for Permit to Drill is for information purposes only and is not an appealable decision.(h) Upon initiation of the Application for Permit to Drill process, the authorized officer shall consult with the appropriate Federal surface management agency and with other interested parties as appropriate and shall take one of the following actions as soon as practical, but in no event later than 5 working days after the conclusion of the 30-day notice period for Federal lands, or within 30 days from receipt of the application for Indian lands: (1) Approve the application as submitted or with appropriate modifications or conditions;(2) Return the application and advise the applicant of the reasons for disapproval; or(3) Advise the applicant, either in writing or orally with subsequent written confirmation, of the reasons why final action will be delayed along with the date such final action can be expected. The surface use plan of operations for National Forest System lands shall be approved by the Secretary of Agriculture or his/her representative prior to approval of the Application for Permit to Drill by the authorized officer. Appeals from the denial of approval of such surface use plan of operations shall be submitted to the Secretary of Agriculture.
(i) Approval of the Application for Permit to Drill does not warrant or certify that the applicant holds legal or equitable title to the subject lease(s) which would entitle the applicant to conduct drilling operations.(j) An Application for Permit to Drill for an oil well with a WMP must include the following information in the WMP: (1) The anticipated initial oil production rate from the oil well and the anticipated production decline over the first 3 years of production;(2) The anticipated initial oil-well gas production rate from the oil well and the anticipated production decline over the first 3 years of production;(3) Certification that the operator has a valid, executed gas sales contract to sell to a purchaser 100 percent of the produced oil-well gas, less gas anticipated for use on-lease pursuant to 43 CFR subpart 3178.(4) Any other information demonstrating the operator's plans to avoid the waste of gas production from any source, including, as appropriate, from pneumatic equipment, storage tanks, and leaks.(k) A self-certification is a written statement that the operator will be able to capture, as defined in 43 CFR 3179.10, 100 percent of the oil-well gas that the oil well produces. An approved Application for Permit to Drill with a self-certification statement is not subject to 43 CFR 3179.70(a), and all flared gas is an avoidable loss with a royalty obligation, except for emergencies as identified in 43 CFR 3179.83 . A self-certification statement applies and is enforceable from the date of first production until the well is plugged and abandoned.(l) The BLM may take one of the following actions based on the operator's WMP or self-certification: (1) Approve an administratively and technically complete oil-well application with a WMP subject to conditions for flared gas, as described in 43 CFR 3179.70(a) ;(2) Approve an administratively and technically complete oil-well application with a self-certification for oil-well gas capture subject to conditions for flared gas, as described in this paragraph;(3) Defer action on an oil-well application with a WMP or self-certification statement that is not administratively and technically complete in the interest of preventing waste until such time as the operator is able to amend the application to comply with the requirements in paragraph (j) of this section or this paragraph, as applicable. If the applicant does not address deficiencies in the WMP or the self-certification to comply with the applicable requirements within 2 years of submission of the application, the BLM will disapprove the application.47 FR 47765, Oct. 27, 1982. Redesignated and amended at 48 FR 36583, Aug. 12, 1983, further amended at 52 FR 5391, Feb. 20, 1987; 53 FR 17363, May 16, 1988; 53 FR 22846, June 17, 1988; 53 FR 31958, Aug. 22, 1988; 81 FR 83078, Nov. 18, 2016; 82 FR 58072, Dec. 8, 2017; 83 FR 49211, Sept. 28, 2018 81 FR 83078, 1/17/2017; 82 FR 58072, 1/8/2018; 83 FR 49211, 11/27/2018; 89 FR 25426, 6/10/2024