43 C.F.R. § 3140.60

Current through November 30, 2024
Section 3140.60 - Use of additional lands
(a) The authorized officer may noncompetitively lease additional lands for ancillary facilities in a Special Tar Sand Area that are needed to support any operations necessary for the recovery of tar sand. Such uses include, but are not limited to, mill site or waste disposal. Application for a lease or permit to use additional lands must be filed under the provisions of 43 CFR part 2920 with the proper BLM office having jurisdiction of the lands. The application for additional lands may be filed at the time a plan of operations is filed.
(b) A lease for the use of additional lands will not be issued when the use can be authorized under 43 CFR parts 2800 and 2880. Such uses include, but are not limited to, reservoirs, pipelines, electrical generation systems, transmission lines, roads, and railroads.
(c) Within units of the National Park System, permits or leases for additional lands will only be issued by the National Park Service. Applications for such permits or leases must be filed with the Regional Director of the National Park Service.

43 C.F.R. §3140.60

89 FR 30988 , 6/22/2024