43 C.F.R. § 3137.73

Current through September 30, 2024
Section 3137.73 - What will BLM do after I submit a plan to meet continuing development obligations?

Within 30 calendar days after receiving your proposed plan, BLM will notify you in writing that we-

(a) Approved your plan;
(b) Rejected your plan and explain why. This will include an explanation of how you should correct the plan to come into compliance; or
(c) Have not acted on the plan, explaining the reasons and when you can expect a final response.

43 C.F.R. § 3137.73