43 C.F.R. § 3000.50

Current through September 30, 2024
Section 3000.50 - Limitations on time to institute suit to challenge a decision of the Secretary

No action challenging a decision of the Secretary involving any oil or gas lease (including decisions on offers or applications to lease) can be maintained unless such action is commenced or taken within 90 days after the final decision of the Secretary relating to such matter.

43 C.F.R. §3000.50

89 FR 30963, 6/22/2024