43 C.F.R. § 426.23

Current through September 30, 2024
Section 426.23 - Recovery of operation and maintenance (O&M) costs
(a)General. All new, amended, and renewed contracts shall provide for payment of O&M costs as specified in this section.
(b)Amount of O&M costs a district must pay if it executes a new or renewed contract. If a district executes a new or renewed contract after October 12, 1982, then that district must pay all of the O&M costs that Reclamation allocates to irrigation.
(c)Amount of O&M costs a district must pay if it amends its contract to conform to the discretionary provisions. If a district has a contract executed prior to October 12, 1982, and the district amends the contract after October 12, 1982, as provided for in § 426.3(a)(2) to conform to the discretionary provisions, then the following applies:
(1) The district must pay all of the O&M costs that Reclamation allocates to irrigation;
(2) If in the year the amendment is executed, the district's contract rate was more than the O&M costs allocated to the district in that year then that positive difference at the time of the contract amendment must continue to be factored into the contract rate and annually paid to the United States. This would be in addition to any adjusted O&M cost that results from paragraph (c)(1) of this section. The positive difference would be factored into the contract rate for the remainder of the term of the contract; and
(3) The district will not be required to pay an increased amount toward the construction costs of a project as a condition of the district's agreeing to a contract amendment pursuant to paragraph (c) of this section.
(d)Amount of O&M cost a district must pay if it amends its contract to provide supplemental or additional benefits. If a district amends its contract after October 12, 1982, to provide supplemental or additional benefits, as provided for in § 426.3(a)(3) , then the following must be complied with:
(1) The district must pay all of the O&M costs that Reclamation allocates to irrigation;
(2) If in the year the amendment is executed, the district's contract rate was more than the O&M costs allocated to the district in that year then that positive difference at the time of the contract amendment must continue to be factored into the contract rate and annually paid to the United States. This would be in addition to any adjusted O&M cost that results from paragraph (d)(1) of this section. The positive difference would be factored into the contract rate for the remainder of the term of the contract; and
(3) The district must pay any increases in the amount paid annually toward the construction costs of a project that the United States requires the district to pay as a condition of agreeing to provide the district with supplemental and additional benefits.
(e)Amount of O&M a district pays under a prior contract. For a district whose prior contract was executed prior to October 12, 1982, the district must pay all of the O&M costs allocated by Reclamation to irrigation unless the contract specifically provides contrary terms.
(f)Amount of O&M that Reclamation charges an irrevocable elector.
(1) Regardless of any terms to the contrary within a prior contract with a district, a landholder who makes an irrevocable election, as provided for in § 426.3(f) must pay, annually, his or her proportionate share of all O&M costs allocated by Reclamation to irrigation. The irrevocable elector's proportionate share is based upon the ratio of:
(i) The amount of land in the district held by the irrevocable elector that received irrigation water to the total amount of land in the district that received irrigation water; or
(ii) The amount of irrigation water in the district received by the irrevocable elector to the total amount of irrigation water that the district delivered.
(2) The district(s) where the irrevocable elector's landholding is located must collect from the irrevocable elector an amount equal to the irrevocable elector's proportionate share of all O&M costs allocated by Reclamation to irrigation and the following apply:
(i) If in the year the election is executed, the district's contract rate was more than the O&M costs allocated to the district in that year, then that positive difference at the time of the contract amendment must continue to be factored into the contract rate. This would be in addition to any adjusted O&M cost that results from paragraph (f)(1) of this section. The positive difference would be factored into the contract rate for the remainder of the term of the contract; and
(ii) Such collections must be forwarded annually to the United States.
(g)Amount of O&M that Reclamation charges if a landholder is subject to full- cost pricing. In a district subject to prior law, if a landholder is subject to full-cost pricing the district must ensure that all O&M costs are included in any full-cost assessment, regardless of whether the landholder is subject to the discretionary provisions. The revenues from such full-cost assessments must be collected and submitted to the United States.

43 C.F.R. §426.23