41 C.F.R. § 102-74.480

Current through September 30, 2024
Section 102-74.480 - How many days does a Federal agency have to issue a permit following receipt of a completed application?

Federal agencies must issue permits within 10 working days following the receipt of the completed applications, unless the permit is disapproved in accordance with § 102-74.500.

41 C.F.R. § 102-74.480