Current through October 31, 2024
Section 265.51 - Purpose and implementation of contingency plan(a) Each owner or operator must have a contingency plan for his facility. The contingency plan must be designed to minimize hazards to human health or the environment from fires, explosions, or any unplanned sudden or non-sudden release of hazardous waste or hazardous waste constituents to air, soil, or surface water.(b) The provisions of the plan must be carried out immediately whenever there is a fire, explosion, or release of hazardous waste or hazardous waste constituents which could threaten human health or the environment.45 FR 33232, May 19, 1980, as amended at 50 FR 4514, Jan. 31, 1985