40 C.F.R. § 122.4

Current through September 30, 2024
Section 122.4 - Prohibitions (applicable to State NPDES programs, see Section 123.25)

No permit may be issued:

(a) When the conditions of the permit do not provide for compliance with the applicable requirements of CWA, or regulations promulgated under CWA;
(b) When the applicant is required to obtain a State or other appropriate certification under section 401 of the CWA and that certification has not been obtained or waived;
(c) By the State Director where the Regional Administrator has objected to issuance of the permit under § 123.44 ;
(d) When the imposition of conditions cannot ensure compliance with the applicable water quality requirements of all affected States;
(e) When, in the judgment of the Secretary, anchorage and navigation in or on any of the waters of the United States would be substantially impaired by the discharge;
(f) For the discharge of any radiological, chemical, or biological warfare agent or high-level radioactive waste;
(g) For any discharge inconsistent with a plan or plan amendment approved under section 208(b) of CWA;
(h) For any discharge to the territorial sea, the waters of the contiguous zone, or the oceans in the following circumstances:
(1) Before the promulgation of guidelines under section 403(c) of CWA (for determining degradation of the waters of the territorial seas, the contiguous zone, and the oceans) unless the Director determines permit issuance to be in the public interest; or
(2) After promulgation of guidelines under section 403(c) of CWA, when insufficient information exists to make a reasonable judgment whether the discharge complies with them.
(i) To a new source or a new discharger, if the discharge from its construction or operation will cause or contribute to the violation of water quality standards. The owner or operator of a new source or new discharger proposing to discharge into a water segment which does not meet applicable water quality standards or is not expected to meet those standards even after the application of the effluent limitations required by sections 301(b)(1)(A) and 301(b)(1)(B) of CWA, and for which the State or interstate agency has performed a pollutants load allocation for the pollutant to be discharged, must demonstrate, before the close of the public comment period, that:
(1) There are sufficient remaining pollutant load allocations to allow for the discharge; and
(2) The existing dischargers into that segment are subject to compliance schedules designed to bring the segment into compliance with applicable water quality standards. The Director may waive the submission of information by the new source or new discharger required by paragraph (i) of this section if the Director determines that the Director already has adequate information to evaluate the request. An explanation of the development of limitations to meet the criteria of this paragraph (i)(2) is to be included in the fact sheet to the permit under § 124.56(b)(1) of this chapter.

40 C.F.R. §122.4

48 FR 14153, Apr. 1, 1983, as amended at 50 FR 6940, Feb. 19, 1985; 65 FR 30905, May 15, 2000; 88 FR 66666, Sept. 27, 2023
88 FR 66666, 11/27/2023