40 C.F.R. § 65.48

Current through September 30, 2024
Section 65.48 - Reporting provisions
(a)Notification of initial startup. If § 65.5(b) requires that a notification of initial startup be filed, then the content of the notification of initial startup shall at least include the information specified in § 65.5(b) and the identification of each storage vessel, its capacity, and the types of regulated material stored in the storage vessel.
(b)Periodic reports. Report the information specified in paragraphs (b)(1) through (3) of this section, as applicable, in the periodic report specified in § 65.5(e) .
(1)Inspection results. Report the following information for each inspection conducted in accordance with § 65.43(c) and § 65.44(c) in which an IFR or EFR failure is detected in the control equipment:
(i) If an IFR type A failure or an EFR failure is observed for vessels for which inspections are required under § 65.43(c)(1)(i) , § 65.43(c)(2)(ii)(A) , or § 65.44(c)(10) , each report shall include the inspection results record listed in § 65.47(c)(1)(ii) . If an extension is utilized in accordance with § 65.43(d)(1) or § 65.44(d)(1) , the report shall include the records listed in § 65.47(c)(1)(ii) plus the documentation specified in § 65.47(d)(1) .
(ii) If an IFR type B failure is observed for vessels for which inspections are required under § 65.43(c)(1)(ii), (c)(2)(i), or (c)(2)(ii)(B) , each report shall include a copy of the records listed in § 65.47(c)(1)(ii) .
(2)Seal gap measurement results.
(i) For each vessel whose seal gaps are measured during the reporting period, identify each seal gap measurement made in accordance with § 65.44(c) in which the requirements of § 65.44(c)(7) or (8) are met.
(ii) For each seal gap measurement made in accordance with § 65.44(c) in which the requirements of § 65.44(c)(7) or (8) are not met, from the records kept pursuant to § 65.47(c)(2) , report the date of the measurements, results of the calculations, and note which seal gap measurements did not conform to the specifications in § 65.44(c)(7) and (8) .
(3)Extension documentation. If an extension is utilized in accordance with § 65.44(c)(9) , the owner or operator shall include the documentation specified in § 65.47(d)(2) in the next report required by § 65.5(e) .
(c)Special notifications. An owner or operator who elects to comply with § 65.43 , § 65.44 , or § 65.45 shall submit, as applicable, the reports specified in paragraphs (c)(1) and (2) of this section except as specified in paragraph (c)(3) of this section. Each written notification or report shall also include the information specified in § 65.5(f) .
(1)Refilling notification. In order to afford the Administrator the opportunity to have an observer present, notify the Administrator prior to refilling of a storage vessel that has been emptied. If the storage vessel is equipped with an internal floating roof as specified in § 65.43 , an external floating roof as specified in § 65.44 , or an external floating roof converted to an internal floating roof as specified in § 65.45 , the notification shall meet either of the following requirements, as applicable.
(i) Notify the Administrator in writing at least 30 calendar days prior to the refilling of each storage vessel; or
(ii) If the inspection is not planned and the owner or operator could not have known about the inspection 30 calendar days in advance of refilling the vessel, the owner or operator shall notify the Administrator as soon as practical, but no later than 7 calendar days prior to the refilling of the storage vessel. Notification may be made by telephone and immediately followed by written documentation demonstrating why the inspection was unplanned. Alternatively, the notification including the written documentation may be made in writing and sent so that it is received by the Administrator at least 7 calendar days prior to refilling.
(2)Seal gap measurement notification. In order to afford the Administrator the opportunity to have an observer present during seal gap measurements, the owner or operator of a storage vessel equipped with an external floating roof as specified in § 65.44 shall meet either of the following notification requirements, as applicable:
(i) Notify the Administrator in writing at least 30 calendar days in advance of any seal gap measurements; or
(ii) If the seal gap measurements are not planned and the owner or operator could not have known about the seal gap measurements 30 calendar days in advance, the owner or operator shall notify the Administrator as soon as practical, but no later than 7 calendar days prior to the seal gap measurements. Notification may be made by telephone and immediately followed by written documentation demonstrating why the seal gap measurements were unplanned. Alternatively, the notification including the written documentation may be made in writing and sent so that it is received by the Administrator at least 7 calendar days prior to refilling.
(3)Notification waiver. Where a notification required by paragraphs (c)(1) or (2) of this section is sent to a delegated State or local agency, a copy of the notification to the Administrator is not required. A delegated State or local agency may waive the requirements for these notifications.
(d)Compliance certification. For sources subject to the compliance certification provisions of title V, a recertification of continuous compliance with §§ 65.43(b)(1) and 65.44(b)(1) shall be based on the annual inspections required by § 65.43(c)(1)(i) and (c)(2)(ii)(A) and any observations made at other times when the roof is viewed.

40 C.F.R. §65.48