40 C.F.R. § 63 app Table 1 to Subpart OOO of Part 63

Current through October 31, 2024
Appendix Table 1 to Subpart OOO of Part 63 - Applicability of General Provisions to Subpart OOO Affected Sources

Reference Applies to subpart OOO Explanation
63.1(a)(1)Yes§ 63.1402 specifies definitions in addition to or that supersede definitions in § 63.2 .
63.1(a)(2)Yes
63.1(a)(3)Yes§ 63.1401(i) identifies those standards which overlap with the requirements of subpart OOO of this part and specify how compliance shall be achieved.
63.1(a)(4)YesSubpart OOO (this table) specifies the applicability of each paragraph in subpart A of this part.
63.1(a)(5)No[Reserved].
63.1(a)(6)Yes
63.1(a)(7)-63.1(a)(9)No[Reserved].
63.1(a)(10)Yes
63.1(a)(11)Yes
63.1(a)(12)-63.1(a)(14)Yes
63.1(b)(1)No
63.1(b)(2)Yes
63.1(b)(3)No§ 63.1400(e) provides documentation requirements for APPUs not considered affected sources.
63.1(c)(1)YesSubpart OOO (this table) specifies the applicability of each paragraph in subpart A of this part.
63.1(c)(2)NoArea sources are not subject to this subpart.
63.1(c)(3)No[Reserved].
63.1(c)(4)No[Reserved].
63.1(c)(5)YesExcept that affected sources are not required to submit notifications overridden by this table.
63.1(c)(6)Yes
63.1(d)No[Reserved].
63.1(e)Yes
63.2Yes§ 63.1402 specifies the definitions from subpart A of this part that apply to this subpart.
63.3Yes
63.4(a)(1)-63.4(a)(3)Yes
63.4(a)(4)No[Reserved].
63.4(a)(5)Yes
63.4(b)Yes
63.4(c)Yes
63.5(a)(1)YesExcept the terms "source" and "stationary source" should be interpreted as having the same meaning as "affected source."
63.5(a)(2)Yes
63.5(b)(1)YesExcept § 63.1400(d) specifies when construction or reconstruction is subject to new source standards.
63.5(b)(2)No[Reserved].
63.5(b)(3)Yes
63.5(b)(4)YesExcept that the Initial Notification and § 63.9(b) requirements do not apply.
63.5(b)(5)Yes
63.5(b)(6)YesExcept that § 63.1400(d) specifies when construction or reconstruction is subject to new source standards.
63.5(c)No[Reserved].
63.5(d)(1)(i)YesExcept that the references to the Initial Notification and § 63.9(b)(5) do not apply.
63.5(d)(1)(ii)YesExcept that § 63.5(d)(1)(ii)(H) does not apply.
63.5(d)(1)(iii)No§ 63.1417(e) specifies Notification of Compliance Status requirements.
63.5(d)(2)No
63.5(d)(3)YesExcept § 63.5(d)(3)(ii) does not apply, and equipment leaks subject to § 63.1410 are exempt.
63.5(d)(4)Yes
63.5(e)Yes
63.5(f)(1)Yes
63.5(f)(2)YesExcept that where § 63.9(b)(2) is referred to, the owner or operator need not comply.
63.6(a)Yes
63.6(b)(1)Yes
63.6(b)(2)Yes
63.6(b)(3)Yes
63.6(b)(4)Yes
63.6(b)(5)Yes
63.6(b)(6)No[Reserved].
63.6(b)(7)No
63.6(c)(1)YesExcept that § 63.1401 specifies the compliance date.
63.6(c)(2)No
63.6(c)(3)No[Reserved].
63.6(c)(4)No[Reserved].
63.6(c)(5)Yes
63.6(d)No[Reserved].
63.6(e)YesExcept as otherwise specified in this table.
63.6(e)(1)(i)NoSee § 63.1400(k)(4) for general duty requirement.
63.6(e)(1)(ii)No
63.6(e)(1)(iii)Yes
63.6(e)(2)Yes
63.6(e)(3)No
63.6(f)(1)No
63.6(f)(2)YesExcept § 63.7(c) , as referred to in § 63.6(f)(2)(iii)(D) , does not apply, and except that § 63.6(f)(2)(ii) does not apply to equipment leaks subject to § 63.1410 .
63.6(f)(3)Yes
63.6(g)Yes
63.6(h)NoThis subpart OOO does not require opacity and visible emission standards.
63.6(i)(1)Yes
63.6(i)(2)Yes
63.6(i)(3)Yes
63.6(i)(4)(i)(A)Yes
63.6(i)(4)(i)(B)NoDates are specified in §§ 63.1401(e) and 63.1417(d)(1) .
63.6(i)(4)(ii)No
63.6(i)(5)-(14)Yes
63.6(i)(15)No[Reserved].
63.6(i)(16)Yes
63.6(j)Yes
63.7(a)(1)Yes
63.7(a)(2)No§ 63.1417(e) specifies the submittal dates of performance test results for all emission points except equipment leaks; for equipment leaks, compliance demonstration results are reported in the Periodic Reports.
63.7(a)(3)Yes
63.7(b)No§ 63.1417 specifies notification requirements.
63.7(c)No
63.7(d)Yes
63.7(e)(1)NoSee § 63.1413(a)(2) .
63.7(e)(2)Yes
63.7(e)(3)NoSubpart OOO specifies requirements.
63.7(e)(4)Yes
63.7(f)YesExcept that if a site specific test plan is not required, the notification deadline in § 63.7(f)(2)(i) shall be 60 days prior to the performance test, and in § 63.7(f)(3) , approval or disapproval of the alternative test method shall not be tied to the site specific test plan.
63.7(g)YesExcept that the requirements in § 63.1417(e) shall apply instead of the references to the Notification of Compliance Status report in § 63.9(h) . In addition, equipment leaks subject to § 63.1410 are not required to conduct performance tests.
63.7(h)YesExcept § 63.7(h)(4)(ii) may not be applicable, if the site-specific test plan in § 63.7(c)(2) is not required.
63.8(a)(1)Yes
63.8(a)(2)No
63.8(a)(3)No[Reserved].
63.8(a)(4)Yes
63.8(b)(1)Yes
63.8(b)(2)NoSubpart OOO specifies locations to conduct monitoring.
63.8(b)(3)Yes
63.8(c)(1)Yes
63.8(c)(1)(i)No
63.8(c)(1)(ii)No
63.8(c)(1)(iii)No
63.8(c)(2)Yes
63.8(c)(3)Yes
63.8(c)(4)No§ 63.1415 specifies monitoring frequency; not applicable to equipment leaks because § 63.1410 does not require continuous monitoring systems.
63.8(c)(5)-63.8(c)(8)No
63.8(d)No
63.8(e)No
63.8(f)(1)-63.8(f)(3)Yes
63.8(f)(4)(i)NoTimeframe for submitting request is specified in § 63.1417 (j) or (k) ; not applicable to equipment leaks because § 63.1410 (through reference to 40 CFR part 63, subpart UU) specifies acceptable alternative methods.
63.8(f)(4)(ii)NoContents of request are specified in § 63.1417(j) or (k) .
63.8(f)(4)(iii)No
63.8(f)(5)(i)Yes
63.8(f)(5)(ii)No
63.8(f)(5)(iii)Yes
63.8(f)(6)NoSubpart OOO does not require continuous emission monitors.
63.8(g)NoData reduction procedures specified in § 63.1416(a) and (h) ; not applicable to equipment leaks.
63.9(a)Yes
63.9(b)NoSubpart OOO does not require an initial notification.
63.9(c)Yes
63.9(d)Yes
63.9(e)No§ 63.1417 specifies notification deadlines.
63.9(f)NoSubpart OOO does not require opacity and visible emission standards.
63.9(g)No
63.9(h)No§ 63.1417(e) specifies Notification of Compliance Status requirements.
63.9(i)Yes
63.9(j)YesFor change in major source status only.
63.9(k)YesOnly as specified in § 63.9(j) .
63.10(a)Yes
63.10(b)(1)No§ 63.1416(a) specifies record retention requirements.
63.10(b)(2)NoSubpart OOO specifies recordkeeping requirements.
63.10(b)(3)No§ 63.1400(e) requires documentation of sources that are not affected sources.
63.10(c)No§ 63.1416 specifies recordkeeping requirements.
63.10(d)(1)Yes
63.10(d)(2)No§ 63.1417 specifies performance test reporting requirements; not applicable to equipment leaks.
63.10(d)(3)NoSubpart OOO does not require opacity and visible emission standards.
63.10(d)(4)Yes
63.10(d)(5)NoSee § 63.1417(g) for malfunction reporting requirements.
63.10(e)No§ 63.1417 specifies reporting requirements.
63.10(f)Yes
63.11YesExcept that instead of § 63.11(b) , § 63.1413(g) shall apply.
63.12Yes
63.13-63.15Yes

40 C.F.R. 63 app Table 1 to Subpart OOO of Part 63

65 FR 3290 , Jan. 20, 2000, as amended at 71 FR 20461 , Apr. 20, 2006; 79 FR 60934 , Oct. 8, 2014; 85 FR 73899 , Nov. 19, 2020
85 FR 73899 , 1/19/2021