40 C.F.R. § 63.1662-63 app Table 7 to Subpart MMMMM of Part 63

Current through October 31, 2024
Appendix Table 7 to Subpart MMMMM of Part 63 - Applicability of General Provisions to Subpart MMMMM

As stated in § 63.8826 , you must comply with the applicable General Provisions requirements according to the following table:

Citation Requirement Applies to subpart MMMMM Explanation
§ 63.1 Initial applicability determination; applicability after standard established; permit requirements; extensions; notificationsYes
§ 63.2 DefinitionsYesAdditional definitions are found in § 63.8830 .
§ 63.3 Units and abbreviationsYes
§ 63.4 Prohibited activities; compliance date; circumvention, severabilityYes
§ 63.5 Construction/reconstruction applicability; applications; approvalsYes
§ 63.6(a) Compliance with standards and maintenance requirements-applicabilityYes
§ 63.6(b)(1)-(4) Compliance dates for new or reconstructed sourcesYes§ 63.8786 specifies compliance dates.
§ 63.6(b)(5) Notification if commenced construction or reconstruction after proposalYes
§ 63.6(b)(6) [Reserved]Yes
§ 63.6(b)(7) Compliance dates for new or reconstructed area sources that become majorYes§ 63.8786 specifies compliance dates.
§ 63.6(c)(1)-(2) Compliance dates for existing sourcesYes§ 63.8786 specifies compliance dates.
§ 63.6(c)(3)-(4) [Reserved]Yes
§ 63.6(c)(5) Compliance dates for existing area sources that become majorYes§ 63.8786 specifies compliance dates.
§ 63.6(d) [Reserved]Yes
§ 63.6(e)(1)(i) General duty to minimize emissionsNo§ 63.8794(c) specifies general duty requirements.
§ 63.6(e)(1)(ii) Requirement to correct malfunctions as soon as possibleNo
§ 63.6(e)(1)(iii) Enforceability of requirements independent of other regulationsYes
§ 63.6(e)(2) [Reserved]Yes
§ 63.6(e)(3) SSM plansNo
§ 63.6(f)(1) Compliance except during SSMNo
§ 63.6(f)(2)-(3) Methods for determining complianceYes
§ 63.6(g) Use of an alternative nonopacity emission standardYes
§ 63.6(h) Compliance with opacity/visible emission standardsNoSubpart MMMMM does not specify opacity or visible emission standards.
§ 63.6(i) Extension of compliance with emission standardsYes
§ 63.6(j) Presidential compliance exemptionYes
§ 63.7(a)(1)-(2) Performance test datesYesExcept for loop slitter affected sources as specified in § 63.8798(a) .
§ 63.7(a)(3) Administrator's section 114 authority to require a performance testYes
§ 63.7(b) Notification of performance test and reschedulingYes
§ 63.7(c) Quality assurance program and site-specific test plansYes
§ 63.7(d) Performance testing facilitiesYes
§ 63.7(e)(1) Conditions for conducting performance testsNoRequirements for performance test conditions are found in § 63.8800(b) and (c) .
§ 63.7(e)(2)-(3) Performance test data reduction and number of test runsYes
§ 63.7(f) Use of an alternative test methodYes
§ 63.7(g) Performance test data analysis, recordkeeping, and reportingYes
§ 63.7(h) Waiver of performance testsYes
§ 63.8(a)(1)-(2) Applicability of monitoring requirementsYesUnless otherwise specified, all of § 63.8 applies only to new or reconstructed flame lamination sources. Additional monitoring requirements for these sources are found in §§ 63.8794(f) and (g) and 63.8804 .
§ 63.8(a)(3) [Reserved]Yes
§ 63.8(a)(4) Monitoring with flaresNoSubpart MMMMM does not refer directly or indirectly to § 63.11 .
§ 63.8(b) Conduct of monitoring and procedures when there are multiple effluents and multiple monitoring systemsYes
§ 63.8(c)(1)-(3) Continuous monitoring system (CMS) operation and maintenanceNoCMS requirements are found in § 63.8794(f) and (g) .
§ 63.8(c)(4) Continuous monitoring system requirements during breakdown, out-of-control, repair, maintenance, and high-level calibration driftsYesApplies as modified by § 63.8794(g) .
§ 63.8(c)(5) Continuous opacity monitoring system (COMS) minimum proceduresNoSubpart MMMMM does not have opacity or visible emission standards.
§ 63.8(c)(6) Zero and high-level calibration checksYesApplies as modified by § 63.8794(f) .
§ 63.8(c)(7)-(8) Out-of-control periods, including reportingYes
§ 63.8(d)-(e) Quality control program and CMS performance evaluationNoCMS requirements are found in § 63.8794(f) and (g) .
§ 63.8(f)(1)-(5) Use of an alternative monitoring methodYes
§ 63.8(f)(6) Alternative to relative accuracy testNoOnly applies to sources that use continuous emissions monitoring systems (CEMS).
§ 63.8(g) Data reductionYesApplies as modified by § 63.8794(g) .
§ 63.9(a) Notification requirements-applicabilityYes
§ 63.9(b) Initial notificationsYesExcept § 63.8816(c) requires new or reconstructed affected sources to submit the application for construction or reconstruction required by § 63.9(b)(1)(iii) in lieu of the initial notification.
§ 63.9(c) Request for compliance extensionYes
§ 63.9(d) Notification that a new source is subject to special compliance requirementsYes
§ 63.9(e) Notification of performance testYes
§ 63.9(f) Notification of visible emissions/opacity testNoSubpart MMMMM does not have opacity or visible emission standards.
§ 63.9(g)(1) Additional CMS notifications-date of CMS performance evaluationYes
§ 63.9(g)(2) Use of COMS dataNoSubpart MMMMM does not require the use of COMS.
§ 63.9(g)(3) Alternative to relative accuracy testingNoApplies only to sources with CEMS.
§ 63.9(h) Notification of compliance statusYes
§ 63.9(i) Adjustment of submittal deadlinesYes
§ 63.9(j) Change in previous informationYes
§ 63.9(k) Electronic reporting proceduresYesOnly as specified in § 63.9(j) .
§ 63.10(a) Recordkeeping/reporting applicabilityYes
§ 63.10(b)(1) General recordkeeping requirementsYes§§ 63.8820 and 63.8822 specify additional recordkeeping requirements.
§ 63.10(b)(2)(i) and (ii) Records related to SSM periods and CMSNoSee § 63.8820 for recordkeeping of (1) date, time, and duration; (2) listing of affected source or equipment, and an estimate of the quantity of each regulated pollutant emitted over the standard; and (3) actions to minimize emissions and correct the failure.
§ 63.10(b)(2)(iii) Records of maintenance on air pollution control equipment.Yes
§ 63.10(b)(2)(iv) and (v) Records related to SSMNo
§ 63.10(b)(2)(vi)-(xi) Records of CMS and other compliance recordsYes
§ 63.10(b)(2)(xii) Records when under waiverYes
§ 63.10(b)(2) (xiii)Records when using alternative to relative accuracy testNoApplies only to sources with CEMS.
§ 63.10(b)(2)(xiv) All documentation supporting initial notification and notification of compliance statusYes
§ 63.10(b)(3) Recordkeeping requirements for applicability determinationsYes
§ 63.10(c) Additional recordkeeping requirements for sources with CMSYesApplies as modified by § 63.8794(g) .
§ 63.10(d)(1) General reporting requirementsYes§ 63.8818 specifies additional reporting requirements.
§ 63.10(d)(2) Performance test resultsYes
§ 63.10(d)(3) Opacity or visible emissions observationsNoSubpart MMMMM does not specify opacity or visible emission standards.
§ 63.10(d)(4) Progress reports for sources with compliance extensionsYes
§ 63.10(d)(5) SSM reportsNo
§ 63.10(e)(1) Additional CMS reports-generalYesApplies as modified by § 63.8794(g) .
§ 63.10(e)(2)(i) Results of CMS performance evaluationsYesApplies as modified by § 63.8794(g) .
§ 63.10(e)(2) Results of continuous opacity monitoring systems performance evaluationsNoSubpart MMMMM does require the use of COMS.
§ 63.10(e)(3) Excess emissions/CMS performance reportsYesOnly applies to new or reconstructed flame lamination affected sources.
§ 63.10(e)(4) Continuous opacity monitoring system data reportsNoSubpart MMMMM does not require the use of COMS.
§ 63.10(f) Recordkeeping/reporting waiverYes
§ 63.11 Control device requirements-applicabilityNoFacilities subject to subpart MMMMM do not use flares as control devices.
§ 63.12 State authority and delegationsYes§ 63.8828 lists those sections of subparts MMMMM and A that are not delegated.
§ 63.13 AddressesYes
§ 63.14 Incorporation by referenceYesSubpart MMMMM does not incorporate any material by reference.
§ 63.15 Availability of information/confidentiality.Yes

40 C.F.R. 63.1662-63 app Table 7 to Subpart MMMMM of Part 63

86 FR 64404 , Nov. 18, 2021
85 FR 73916, 1/19/2021; 86 FR 64404, 11/18/2021