General provisions citation | Subject of citation | Applies to subpart TTTT | Explanation |
§ 60.1 | Applicability | Yes | |
§ 60.2 | Definitions | Yes | Additional terms defined in § 60.5580 . |
§ 60.3 | Units and Abbreviations | Yes | |
§ 60.4 | Address | Yes | Does not apply to information reported electronically through ECMPS. Duplicate submittals are not required. |
§ 60.5 | Determination of construction or modification | Yes | |
§ 60.6 | Review of plans | Yes | |
§ 60.7 | Notification and Recordkeeping | Yes | Only the requirements to submit the notifications in § 60.7(a)(1) and (3) and to keep records of malfunctions in § 60.7(b) , if applicable. |
§ 60.8(a) | Performance tests | No | |
§ 60.8(b) | Performance test method alternatives | Yes | Administrator can approve alternate methods |
§ 60.8(c)-(f) | Conducting performance tests | No | |
§ 60.9 | Availability of Information | Yes | |
§ 60.10 | State authority | Yes | |
§ 60.11 | Compliance with standards and maintenance requirements | No. | |
§ 60.12 | Circumvention | Yes | |
§ 60.13 (a)-(h), (j) | Monitoring requirements | No | All monitoring is done according to part 75. |
§ 60.13 (i) | Monitoring requirements | Yes | Administrator can approve alternative monitoring procedures or requirements |
§ 60.14 | Modification | Yes (steam generating units and IGCC facilities) No (stationary combustion turbines) | |
§ 60.15 | Reconstruction | Yes | |
§ 60.16 | Priority list | No | |
§ 60.17 | Incorporations by reference | Yes | |
§ 60.18 | General control device requirements | No | |
§ 60.19 | General notification and reporting requirements | Yes | Does not apply to notifications under § 75.61 or to information reported through ECMPS. |
40 C.F.R. §Table 3 of Subpart TTTT of Part 60