40 C.F.R. § 60.4800

Current through July 31, 2024
Section 60.4800 - Who must prepare a siting analysis?
(a) You must prepare a siting analysis if you plan to commence construction of a SSI unit after October 14, 2010.
(b) You must prepare a siting analysis if you are required to submit an initial application for a construction permit under 40 CFR part 51, subpart I, or 40 CFR part 52, as applicable, for the modification of your SSI unit.

40 C.F.R. §60.4800