40 C.F.R. § 60.2600

Current through October 31, 2024
Section 60.2600 - How do I comply with the increment of progress for submittal of a control plan?

For your control plan increment of progress, you must satisfy the two requirements specified in paragraphs (a) and (b) of this section:

(a) Submit the final control plan that includes the five items described in paragraphs (a)(1) through (5) of this section:
(1) A description of the devices for air pollution control and process changes that you will use to comply with the emission limitations and other requirements of this subpart;
(2) The type(s) of waste to be burned;
(3) The maximum design waste burning capacity;
(4) The anticipated maximum charge rate; and
(5) If applicable, the petition for site-specific operating limits under § 60.2680 .
(b) Maintain an onsite copy of the final control plan.

40 C.F.R. §60.2600

81 FR 41001, 6/23/2016; 84 FR 15884, 4/16/2019