40 C.F.R. § 60.32d

Current through July 31, 2024
Section 60.32d - Compliance times

Sulfuric acid production units. Planning, awarding of contracts, and installation of equipment capable of attaining the level of the emission guideline established under § 60.31d can be accomplished within 17 months after the effective date of a State emission standard for sulfuric acid mist.

40 C.F.R. §60.32d