Figure 1-Summary Report-Gaseous and Opacity Excess Emission and Monitoring System Performance
Pollutant (Circle One-SO2/NOX/TRS/H2S/CO/Opacity)
Reporting period dates: From ____________________ to ____________________
Company:
Emission Limitation _______________________________
Address:
Monitor Manufacturer and Model No. _______________________________
Date of Latest CMS Certification or Audit _______________________________
Process Unit(s) Description:
Total source operating time in reporting period1 _______________________________
Emission data summary1 | CMS performance summary1 | ||
1. Duration of excess emissions in reporting period due to: | 1. CMS downtime in reporting period due to: | ||
a. Startup/shutdown | a. Monitor equipment malfunctions | ||
b. Control equipment problems | b. Non-Monitor equipment malfunctions | ||
c. Process problems | c. Quality assurance calibration | ||
d. Other known causes | d. Other known causes | ||
e. Unknown causes | e. Unknown causes | ||
2. Total duration of excess emission | 2. Total CMS Downtime | ||
3. Total duration of excess emissions * (100) [Total source operating time] | %2 | 3. [Total CMS Downtime] * (100) [Total source operating time] | %2 |
1 For opacity, record all times in minutes. For gases, record all times in hours.
2 For the reporting period: If the total duration of excess emissions is 1 percent or greater of the total operating time or the total CMS downtime is 5 percent or greater of the total operating time, both the summary report form and the excess emission report described in § 60.7(c) shall be submitted.
On a separate page, describe any changes since last quarter in CMS, process or controls. I certify that the information contained in this report is true, accurate, and complete.
_______________________________
Name
_______________________________
Signature
_______________________________
Title
_______________________________
Date
40 C.F.R. §60.7