Current through October 31, 2024
Section 57.705 - Contents of SIP Compliance Schedule required by Section 57.201(d) (2) and (3)This section applies to smelters which are required to submit a SIP Compliance Schedule as discussed below.
(a) Each SIP Compliance Schedule required by § 57.201(d) (2) and (3) must contain the following elements: (1) Description of the overall design of the SO2 control system(s) to be installed;(2) Descriptions of specific process hardware to be used in achieving compliance with the SIP emission limitation including gas capacity values;(3) The date by which contracts will be let or purchase orders issued to accomplish any necessary performance improvements;(4) The date for initiating on-site construction or installation of necessary equipment;(5) The date by which on-site construction or installation of equipment is to be completed;(6) The date for achievement of final compliance with SIP emission limitations; and(7) Any other measures necessary to assure compliance with all SIP requirements as expeditiously as practicable.(b)Operations of SCS. Smelters to which § 57.705 is applicable must comply with all elements of § 57.703 .