Contaminants | Averaging time (hours) | Stage 1 | Stage 2 | Stage 3 |
Nitrogen dioxide | 1 | 0.6 ppm | 1.2 ppm | 1.6 ppm. |
24 | 0.15 ppm | 0.3 ppm | 0.4 ppm. | |
Particulate matter | 24 | 3.0 COH | 5.0 COH | 7.0 COH. |
24 | 375 ugm-3 | 625 ugm-3 | 875 ugm-3. | |
Sulfur dioxide and particulate matter combined | 24 | 0.21 | 0.81 | 1.21. |
24 | 65,0002 | 261,0002 | 393,0002. |
1 Product of sulfur dioxide (ppm) and particulate matter (COH).
2 Product of sulfur dioxide (ugm-3 ) and particulate matter (ugm-3 ).
Environmental Protection Agency, Air and Hazardous Materials Division (A-4), Attn: Air Programs Branch, 215 Fremont Street, San Francisco, Calif. 94105.
Pollutant | Averaging time (hours) | Stage 1 | Stage 2 | Stage 3 |
Carbon monoxide | 4 | 1 25 | 1 45 | 1 60 |
8 | 1 15 | 1 30 | 1 40 |
1 Parts per million by volume.
Pollutant | Averaging time (hours) | Stage 1 | Stage 2 | Stage 3 |
Particulate matter | 24 | 1 375 | 1 625 | 1 875 |
1 Micrograms per cubic meter.
Regional Administrator, Attn: Air and Hazardous Materials Division, Air Technical Branch, Technical Analysis Section (A-4-3), Environmental Protection Agency, 215 Fremont Street, San Francisco CA 94105.
Pollutant | Averaging time (hours) | [MICRO]g/m3 | ||
Stage 1 | Stage 2 | Stage 3 | ||
Particulate matter | 24 | 375 | 625 | 875 |
Pollutant | Averaging time (hours) | Stage 1 (ppm) | Stage 2 (ppm) | Stage 3 (ppm) |
Carbon monoxide | 4 | 25 | 45 | 60 |
8 | 15 | 30 | 40 |
Regional Administrator, ATTN: Air and Hazardous Materials Division, Air Technical Branch, Technical Analysis Section (A-4-3), Environmental Protection Agency, 215 Fremont Street, San Francisco, CA 94105.
Pollutant | Averaging time (hours) | [MICRO]g/m3 | ||
Stage 1 | Stage 2 | Stage 3 | ||
Particulate matter | 24 | 375 | 625 | 875 |
Photochemical oxidants | 1 | 1 0.5 |
1 Parts per million.
40 C.F.R. §52.274
For FEDERAL REGISTER citations affecting §52.274, see the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and at www.govinfo.gov.