40 C.F.R. § 35.6610

Current through September 30, 2024
Section 35.6610 - Contracts awarded by a contractor

The recipient must require its contractor to comply with the following provisions in the award of contracts (i.e. subcontracts). (This section does not apply to a supplier's procurement of materials to produce equipment, materials and catalog, off-the-shelf, or manufactured items.)

(a) The requirements referenced in § 35.6020 .
(b) The limitations on contract award in § 35.6550(a)(6) .
(c) [Reserved]
(d) The requirements regarding specifications in § 35.6555 (a)(6) and (c) .
(e) The Federal cost principles in 2 CFR part 200 subpart E.
(f) The prohibited types of contracts in § 35.6575(a) .
(g) The cost, price analysis, and profit analysis requirements in § 35.6585 .
(h) The applicable provisions in § 35.6595 (b) .
(i) The applicable provisions in § 35.6555(b)(2) .

40 C.F.R. §35.6610

72 FR 24504, May 2, 2007, as amended at 73 FR 15922, Mar. 26, 2008; 79 FR 76061, Dec. 19, 2014