40 C.F.R. § 35.4012

Current through September 30, 2024
Section 35.4012 - If there appears to be a difference between the requirements of 2 CFR Parts 200 and 1500 and this subpart, which regulations should my group follow?

You should follow the regulations in 2 CFR part 200 and 2 CFR part 1500, except for the following provisions from which this subpart deviates:

(a)2 CFR 200.305(b)(1) and (2) , Payment
(b)2 CFR 200.320 , Methods of procurement to be followed.
(c)2 CFR 200.325(b)(2) , Federal awarding agency or pass-through entity review.
(d)2 CFR 200.324 , Cost or price analysis.
(e) 2 CFR part 1500 Subpart E-Disputes.

40 C.F.R. §35.4012

65 FR 58858, Oct. 2, 2000, as amended at 79 FR 76058, Dec. 19, 2014; 87 FR 30400, May 19, 2022
87 FR 30400, 5/19/2022