4 C.F.R. § 21.6

Current through November 30, 2024
Section 21.6 - Withholding of award and suspension of contract performance

When a protest is filed, the agency may be required to withhold award and to suspend contract performance. The requirements for the withholding of award and the suspension of contract performance are set forth in 31 U.S.C. 3553(c) and (d) ; GAO does not administer the requirements to withhold award or suspend contract performance. An agency shall file a notification in instances where it overrides a requirement to withhold award or suspend contract performance, and it shall file either a copy of any issued determination and finding, or a statement by the individual who approved the determination and finding that explains the statutory basis for the override.

4 C.F.R. §21.6

83 FR 13824 , Apr. 2, 2018
83 FR 13824 , 5/1/2018