36 C.F.R. § 9.170

Current through October 31, 2024
Section 9.170 - When must I plug my well?

Except as provided in § 9.171 , you must plug your well when any of the following occurs:

(a) Your drilling operations have ended and you have taken no further action to produce the well within 60 days;
(b) Your well, which has been completed for production operations, has no measureable production quantities for 12 consecutive months; or
(c) The period approved in your operations permit to maintain your well in shut-in status has expired.

36 C.F.R. §9.170

81 FR 77992 , 12/5/2016