36 C.F.R. § 51.57

Current through October 31, 2024
Section 51.57 - How does a concessioner request arbitration of the construction cost of a capital improvement?

If a concessioner requests arbitration of the construction cost of a capital improvement determined by the Director, the request must be made in writing to the Director within 3 months of the date of the Director's determination of construction cost under § 51.56 . The arbitration procedures are described in § 51.51 . The decision of the arbitration panel as to the construction cost of the capital improvement will be binding on the concessioner and the Director.

36 C.F.R. §51.57

66 FR 35083 , July 3, 2001