33 C.F.R. § 402.14

Current through September 30, 2024
Section 402.14 - Operational surcharges-after postponements

ItemColumn 1
Place in Montreal-Lake Ontario
Column 2
Period after clearance date
Column 3
Amount ($)
(5 locks)1
(a)Cape Vincent (downbound) or Cape Saint-Michel (upbound):
(1) If the postponement is for 24 hours(a) 24 hours or more but less than 36 hours20,000
(b) 36 hours or more but less than 48 hours40,000
(c) 48 hours or more but less than 72 hours60,000
(d) 72 hours or more but less than 96 hours80,000
(2) If the postponement is for 48 hours(a) 48 hours or more but less than 56 hours20,000
(b) 56 hours or more but less than 64 hours40,000
(c) 64 hours or more but less than 72 hours60,000
(d) 72 hours or more but less than 96 hours80,000
(3) If the postponement is for 72 hours(a) 72 hours or more but less than 78 hours20,000
(b) 78 hours or more but less than 84 hours40,000
(c) 84 hours or more but less than 90 hours60,000
(d) 90 hours or more but less than 96 hours80,000
(b)Port, dock or wharf within St. Lambert-Iroquois lock segment:
(1) If the postponement is for 24 hours(a) 24 hours or more but less than 48 hoursn/a
(b) 48 hours or more but less than 60 hours20,000
(c) 60 hours or more but less than 72 hours40,000
(d) 72 hours or more but less than 96 hours60,000
(2) If the postponement is for 48 hours(a) 48 hours or more but less than 72 hoursn/a
(b) 72 hours or more but less than 80 hours20,000
(c) 80 hours or more but less than 88 hours40,000
(d) 88 hours or more but less than 96 hours60,000
(3) If the postponement is for 72 hours or more(a) 72 hours or more but less than 96 hoursn/a

1 Prorated on a per-lock basis.