Table 155.5050(g)-Response Times for Tier 1
Tier 1 | |
Higher volume port area | 12 hrs. |
Great Lakes | 18 hrs. |
All other operating environments, including rivers and canals, inland, nearshore, offshore, and open ocean areas | 24 hrs. |
Table 155.5050(p)-Nontank Vessel Response Plan Required Response Resources Matrix
Nontank vessel's fuel or cargo oil capacity | AMPD | MMPD | WCD | Salvage | Emergency lightering | Fire fighting | Dispersant3 | Aerial tracking4 | Shoreline protection | Shore line cleanup |
2,500 barrels or greater | NO1 | YES | YES | YES | YES | YES | YES | YES | YES | YES. |
Less than 2,500 barrels, but greater than or equal to 250 barrels | NO1 | YES | NO | YES2 | YES2 | YES2 | YES2 | YES2 | YES | YES. |
Less than 250 barrels | NO1 | YES2 | NO | YES2 | NO | NO | NO | NO | NO | NO. |
1 For nontank vessels carrying oil as fuel only. Nontank vessels carrying oil as cargo must meet AMPD response resources in 33 CFR 155.5050(d)(1) as applicable.
2 The indicated response resources that must be located within the stipulated response times in the specified geographic areas need only be identified and planned for in the VRP, but not ensured available by contract. Submission of a written consent from the response resource provider must accompany the VRP for approval. This is considered an acceptable "other approved means." See 33 CFR 155.5020 , "Contract or other approved means", paragraph (5).
33 C.F.R. §155.5050