The District Commander must be notified of the following:
When- | The District Commander must be notified- |
(a) Construction of a pipeline, platform, or single point mooring (SPM) is planned | At least 30 days before construction begins. |
(b) Construction of a pipeline, platform, or SPM begins | Within 24 hours, from the date construction begins, that the lights and sound signals are in use at the construction site. |
(c) A light or sound signal is changed during construction | Within 24 hours of the change. |
(d) Lights or sound signals used during construction of a platform, buoy, or SPM are replaced by permanent fixtures to meet the requirements of this part | Within 24 hours of replacement. |
(e) The first cargo transfer operation begins | At least 60 days before the operation. |
33 C.F.R. §149.610