Current through September 30, 2024
Section 127.321 - Release of LNG(a) The operator of the waterfront facility handling LNG must ensure that-(1) No person releases LNG into the navigable waters of the United States; and(2) If there is a release of LNG, vessels near the facility are notified of the release by the activation of the warning alarm.(b) If there is a release of LNG, the person in charge of shoreside transfer operations must- (1) Immediately notify the person in charge of cargo transfer on the vessel of the intent to shutdown;(2) Shutdown transfer operations;(3) Notify the COTP of the release; and(4) Not resume transfer operations until authorized by the COTP.CGD 78-038, 53 FR 3376, Feb. 7, 1988, as amended by CGD 88-049, 60 FR 39796, Aug. 3, 1995; USCG-2019-0444, 87 FR 5691, Feb. 2, 2022