Current through September 30, 2024
Section 117.731 - Mullica RiverThe draws of the bridges listed in this section shall open on signal, except as follows:
(a) The draw of the Lower Bank bridge, mile 15.0, need not open during the following periods unless at least four hours notice is given: (1) From May 1 through November 30, from 11 p.m. to 7 a.m.(2) From December 1 through April 30, at all times.(b) The draw of the Green Bank bridge, mile 18.0, need not open unless at least four hours notice is given during the following periods:(1) April 1 through November 30, from 11 p.m. to 7 a.m.(2) December 1 through March 31, at all times.(c) The drawspan must open as soon as possible for public vessels of the United States during the periods when four hours notice is required.CGD5-87-065, 53 FR 406, Jan. 7, 1988, as amended by CGD05 94-093, 60 FR 51732, Oct. 3, 1995. Redesignated and amended by USCG-2001-10881, 71 FR 70311, Dec. 4, 2006