30 C.F.R. § 784.19

Current through November 30, 2024
Section 784.19 - Underground development waste

Each plan shall contain descriptions, including appropriate maps and cross section drawings of the proposed disposal methods and sites for placing underground development waste and excess spoil generated at surface areas affected by surface operations and facilities, according to 30 CFR 817.71 through 817.74 . Each plan shall describe the geotechnical investigation, design, construction, operation, maintenance and removal, if appropriate, of the structures and be prepared according to 30 CFR 780.35 .

30 C.F.R. §784.19

79 FR 76230 , Dec. 22, 2014, as amended at 81 FR 93355 , Dec. 20, 2016; 82 FR 54958 , Nov. 17, 2017
81 FR 93355 , 1/19/2017