You must notify BOEM any time you cease activities under your approved GAP without an approved suspension. If you cease activities for an indefinite period that exceeds 6 months, BOEM may cancel your lease or grant under § 585.422 , as applicable, and you must initiate the decommissioning process, as set forth in 30 CFR part 285, subpart I.
30 C.F.R. §585.656