Current through November 30, 2024
Section 285.910 - What must I do when I remove my facility?(a) You must remove all facilities to a depth of 15 feet below the mudline, unless otherwise authorized by BSEE.(b) Within 60 days after you remove a facility, you must verify to BSEE that you have cleared the site.