The lessee shall comply with the following requirements during well-workover operations with the tree removed:
If you have . . . | you must equip . . . | so you can monitor . . . |
(i) fixed platform wells, | the wellhead, | all annuli (A, B, C, D, etc., annuli). |
(ii) subsea wells, | the tubing head, | the production casing annulus (A annulus). |
(iii) hybrid* wells, | the surface wellhead, | all annuli at the surface (A and B riser annuli). If the production casing below the mudline and the production casing riser above the mudline are pressure isolated from each other, provisions must be made to monitor the production casing below the mudline for casing pressure. |
* Characterized as a well drilled with a subsea wellhead and completed with a surface casing head, a surface tubing head, a surface tubing hanger, and a surface christmas tree.
30 C.F.R. §250.619