Section 250.529 - What are the terms of my casing pressure request?

Casing pressure requests are approved by the Regional Supervisor, Field Operations, for a term to be determined by the Regional Supervisor on a case-by-case basis. The Regional Supervisor may impose additional restrictions or requirements to allow continued operation of the well.

30 C.F.R. §250.529

76 FR 64462, Oct. 18, 2011. Redesignated at 77 FR 50894, Aug. 22, 2012