30 C.F.R. § 250.525

Current through November 30, 2024
Section 250.525 - When am I required to take action from my casing diagnostic test?

You must take action if you have any of the following conditions:

(a) Any fixed platform well with a casing pressure exceeding its maximum allowable wellhead operating pressure (MAWOP);
(b) Any fixed platform well with a casing pressure that is greater than 100 psig and that cannot bleed to 0 psig through a 1/2-inch needle valve within 24 hours, or is not bled to 0 psig during a casing diagnostic test;
(c) Any well that has demonstrated tubing/casing, tubing/riser, casing/casing, riser/casing, or riser/riser communication;
(d) Any well that has sustained casing pressure (SCP) and is bled down to prevent it from exceeding its MAWOP, except during initial startup operations described in § 250.522 ;
(e) Any hybrid well with casing or riser pressure exceeding 100 psig; or
(f) Any subsea well with a casing pressure 100 psig greater than the external hydrostatic pressure at the subsea wellhead.

30 C.F.R. §250.525

76 FR 64462 , Oct. 18, 2011. Redesignated at 77 FR 50894 , Aug. 22, 2012; 84 FR 21976 , May 15, 2019
84 FR 21976 , 7/15/2019