30 C.F.R. § 250.519

Current through November 30, 2024
Section 250.519 - What are the requirements for casing pressure management?

Once you install your wellhead, you must meet the casing pressure management requirements of API RP 90 (as incorporated by reference in § 250.198 ) and the requirements of §§ 250.519 through 250.531 . If there is a conflict between API RP 90 and the casing pressure requirements of this subpart, you must follow the requirements of this subpart.

30 C.F.R. §250.519

84 FR 21976 , May 15, 2019
84 FR 21976 , 7/15/2019