30 C.F.R. § 250.519

Current through September 30, 2024
Section 250.519 - What are the requirements for casing pressure management?

Once you install your wellhead, you must meet the casing pressure management requirements of API RP 90 (as incorporated by reference in § 250.198 ) and the requirements of §§ 250.519 through 250.531 . If there is a conflict between API RP 90 and the casing pressure requirements of this subpart, you must follow the requirements of this subpart.

30 C.F.R. §250.519

84 FR 21976, May 15, 2019
84 FR 21976, 7/15/2019