Current through November 30, 2024
Section 250.460 - What are the requirements for conducting a well test?(a) If you intend to conduct a well test, you must include your projected plans for the test with your APD (form BSEE-0123) or in an Application for Permit to Modify (APM) (form BSEE-0124). Your plans must include at least the following information:(1) Estimated flowing and shut-in tubing pressures;(2) Estimated flow rates and cumulative volumes;(3) Time duration of flow, buildup, and drawdown periods;(4) Description and rating of surface and subsurface test equipment;(5) Schematic drawing, showing the layout of test equipment;(6) Description of safety equipment, including gas detectors and fire-fighting equipment;(7) Proposed methods to handle or transport produced fluids; and(8) Description of the test procedures.(b) You must give the District Manager at least 24-hours notice before starting a well test.