30 C.F.R. § 250.287

Current through September 30, 2024
Section 250.287 - [Effective until 10/29/2024] For what development projects must I submit a DWOP?

You must submit a DWOP for each development project in which you will use non-conventional production or completion technology, regardless of water depth. If you are unsure whether BSEE considers the technology of your project non-conventional, you must contact the Regional Supervisor for guidance.

30 C.F.R. §250.287