25 C.F.R. § 273.157

Current through October 31, 2024
Section 273.157 - What is the process for requesting technical assistance and/or training?
(a) Existing contracting parties may request technical assistance and/or training by addressing the request in writing to the BIE Director.
(b) The BIE Director, or designee, will acknowledge receipt of a request for technical assistance and/or training.
(c) No later than 30 days after receiving the original request, the BIE Director will identify a point of contact and begin the process of providing technical assistance and/or training. The BIE Director and requesting contracting party will work together to identify the form, substance, and timeline for the assistance.

25 C.F.R. §273.157

85 FR 10948 , 3/26/2020