25 C.F.R. § 175.215

Current through September 30, 2024
Section 175.215 - What is BIA's procedure for adjusting electric power rates?

Except for purchased power costs, if we determine electric power rates need to be adjusted, we will:

(a) Hold public meetings and notify you of their respective time, date, and location by newspaper notice and a notice posted in the utility office serving you;
(b) Provide you notice at least 15 days prior to the meeting;
(c) Provide you a description of the proposed rate adjustment;
(d) Provide you information on how, where, and when to submit comments on our proposed rate adjustment;
(e) Make a final determination on the proposed rate adjustment after all comments have been received, reviewed, and evaluated; and
(f) Publish the proposed rate adjustment and the final rate in the FEDERAL REGISTER if we determine the rate adjustment is necessary.

25 C.F.R. §175.215

83 FR 61119, 12/28/2018