24 C.F.R. § 245.425

Current through November 30, 2024
Section 245.425 - Submission of request for approval to HUD

Upon completion of the tenant comment period, the mortgagor must review the comments submitted by tenants and their representatives and prepare a written evaluation of the comments. The mortgagor must then submit the following materials to the local HUD office:

(a) The mortgagor's written request for HUD approval of the covered action;
(b) Copies of all written tenant comments;
(c) The mortgagor's evaluation of the tenant comments on the proposed conversion or reduction;
(d) A certification by the mortgagor that it has complied with all of the requirements of § 245.410 , § 245.415 , §§ 245.416 through 245.419 , as applicable, § 245.420 , and this section; and
(e) Such additional materials as HUD may have specified in writing.