24 C.F.R. § 50.36

Current through November 30, 2024
Section 50.36 - Updating of environmental reviews

The environmental review must be re-evaluated and updated when the basis for the original environmental or compliance findings is affected by a major change requiring HUD approval in the nature, magnitude or extent of a project and the project is not yet complete. A change only in the amount of financing or mortgage insurance involved does not normally require the environmental review to be re-evaluated or updated.

24 C.F.R. § 50.36