23 C.F.R. § 661.37

Current through September 30, 2024
Section 661.37 - What are the funding limitations on an individual TTF bridge project?

The following funding provisions apply in administration of the TTFBP:

(a) There are no funding limitations on an individual TTF bridge application, but the PE estimated cost will be based on the following fee scale:

Estimated Construction Cost:

Up to $1,000,000-Use up to 20% for PE

$1,000,000 to $5,000,000-Use up to 15%-20% for PE

$5,000,000 to $10,000,000-Use up to 10%-15% for PE

Over $10,000,000-Use up to 10% for PE

(b) Requests for additional funds for PE or construction may be submitted along with proper justification to FHWA for consideration. The request will be considered on a case-by-case basis. There is no guarantee for the approval of the request for additional funds.

23 C.F.R. §661.37

89 FR 57082, 8/12/2024