Time in months following conversion from "E" (bond issue) project to regular project | Cumulative amount reimbursable (percent of Federal funds obligated) |
1 | 1 |
2 | 2 |
3 | 5 |
4 | 9 |
5 | 13 |
6 | 18 |
7 | 23 |
8 | 29 |
9 | 34 |
10 | 39 |
11 | 44 |
12 | 49 |
13 | 54 |
14 | 58 |
15 | 61 |
16 | 64 |
17 | 67 |
18 | 70 |
19 | 73 |
20 | 75 |
21 | 77 |
22 | 79 |
23 | 81 |
24 | 83 |
25 | 85 |
26 | 87 |
27 | 89 |
28 | 91 |
29 | 93 |
30 | 94 |
31 | 95 |
32 | 96 |
34 | 97 |
35 | 99 |
36 | 100 |
23 C.F.R. § 140 app to Subpart F of Part 140