Current through October 31, 2024
Section 411.625 - Can the beneficiary or the EN that is not a State VR agency request a review of the PM's recommendation?(a) Yes. After receiving the PM's recommendation, either the beneficiary or the EN may request a review by us. The request must be in writing and received by the PM within 15 working days of the receipt of the PM's recommendation for resolving the dispute.(b) The PM has 10 working days to refer the request for a review to us. The request for a review must include:(1) A copy of the beneficiary's IWP;(2) Information and evidence related to the disputed issue(s); and(3) The PM's conclusion(s) and recommendation(s).