Current through November 30, 2024
Section 806.4 - Projects requiring review and approval(a) Except for activities relating to site evaluation, to aquifer testing under § 806.12 or to those activities authorized under § 806.34 , no person shall undertake any of the following projects without prior review and approval by the Commission. The project sponsor shall submit an application in accordance with subpart B of this part and shall be subject to the applicable standards in subpart C of this part.(1)Consumptive use of water. Any consumptive use project described in this paragraph (a)(1) shall require an application to be submitted in accordance with § 806.13 , and shall be subject to the standards set forth in § 806.22 , and, to the extent that it involves a withdrawal from groundwater or surface water except a small capacity source, shall also be subject to the standards set forth in § 806.23 as the Commission deems necessary. Except to the extent that they involve the diversion of the waters of the basin, public water supplies shall be exempt from the requirements of this section regarding consumptive use; provided, however, that nothing in this section shall be construed to exempt individual consumptive users connected to any such public water supply from the requirements of this section. Provided the commission determines that low flow augmentation projects sponsored by the commission's member states provide sufficient mitigation for agricultural water use to meet the standards set forth in § 806.22 , and except as otherwise provided in this paragraph (a)(1), agricultural water use projects shall not be subject to the requirements of this paragraph (a)(1). Notwithstanding the foregoing, an agricultural water use project involving a diversion of the waters of the basin shall be subject to such requirements unless the property, or contiguous parcels of property, upon which the agricultural water use project occurs is located at least partially within the basin. (i) Any project initiated on or after January 23, 1971, involving a consumptive water use of an average of 20,000 gallons per day (gpd) or more in any consecutive 30-day period.(ii) With respect to projects previously approved by the Commission for consumptive use, any project that will involve an increase in a consumptive use above that amount which was previously approved.(iii) With respect to projects with pre-compact consumptive use:(A) Registered in accordance with subpart E of this part that increases its consumptive use by any amount over the quantity determined under § 806.44 ;(B) Increasing its consumptive use to an average of 20,000 gpd or more in any consecutive 30-day period; or(C) That failed to register its consumptive use in accordance with subpart E of this part.(iv) Any project, regardless of when initiated, involving a consumptive use of an average of 20,000 gpd or more in any consecutive 30-day period, and undergoing a change of ownership, unless such project satisfies the requirements of paragraph (b) of this section or the existing Commission approval for such project is transferred pursuant to § 806.6 .(2)Withdrawals. Any project, including all of its sources, described in this paragraph (a)(2) shall require an application to be submitted in accordance with § 806.13 , and shall be subject to the standards set forth in §§ 806.21 and 806.23 . Hydroelectric projects, except to the extent that such projects involve a withdrawal, shall be exempt from the requirements of this section regarding withdrawals; provided, however, that nothing in this paragraph (a)(2) shall be construed as exempting hydroelectric projects from review and approval under any other category of project requiring review and approval as set forth in this section, § 806.5 , or 18 CFR part 801 . (i) Any project initiated on or after July 13, 1978 for groundwater or November 11, 1995 for surface water withdrawing a consecutive 30-day average of 100,000 gpd or more from a groundwater or surface water source, or any project initiated after January 1, 2007 withdrawing a consecutive 30-day average of 100,000 gpd or more from a combination of sources.(ii) Any new source added to projects with previously approved withdrawals by the Commission.(iii) Any withdrawal increased above that amount which was previously approved by the Commission.(iv) With respect to projects with grandfathered withdrawals:(A) Registered in accordance with subpart E of this part that increases its withdrawal by any amount over the quantity determined under § 806.44 ;(B) Increasing its withdrawal individually or in combination from all sources to an average of 100,000 gpd or more in any consecutive 30-day period; or(C) That failed to register its withdrawals in accordance with subpart E of this part.(v) Any project, regardless of when initiated, involving a withdrawal of a consecutive 30-day average of 100,000 gpd or more, from either groundwater or surface water sources, or in combination from both, and undergoing a change of ownership, unless such project satisfies the requirements of paragraph (b) of this section or the existing Commission approval for such project is transferred pursuant to § 806.6 .(3)Diversions. Except with respect to agricultural water use projects not subject to the requirements of paragraph (a)(1) of this section, the projects described in paragraphs (a)(3)(i) through (iv) of this section shall require an application to be submitted in accordance with § 806.13 , and shall be subject to the standards set forth in § 806.24 . The project sponsors of out-of-basin diversions shall also comply with all applicable requirements of this part relating to consumptive uses and withdrawals. The projects identified in paragraphs (a)(3)(v) and (vi) of this section shall be subject to regulation pursuant to § 806.22(f) . (i) Any project initiated on or after January 23, 1971, involving the diversion of water into the basin by any amount, or involving a diversion of water out of the basin of an average of 20,000 gallons of water per day or more in any consecutive 30-day period.(ii) With respect to diversions previously approved by the Commission, any project that will increase a diversion above the amount previously approved.(iii) With respect to diversions initiated prior to January 23, 1971, any project that will increase a diversion into the basin by any amount, or increase the diversion of water out of the basin by any amount.(iv) Any project, regardless of when initiated, involving the diversion of water into the basin by any amount or involving a diversion of water out of the basin by an average of 20,000 gallons of water per day or more in any consecutive 30-day period, and undergoing a change of ownership, unless such project satisfies the requirements of paragraph (b) of this section or the Commission approval for such project is transferred pursuant to § 806.6 .(v) The interbasin diversion of any flowback or production fluids, tophole water and captured stormwater from hydrocarbon development projects from one drilling pad site to another drilling pad site for use in hydrofracture stimulation, provided it is handled, transported and stored in compliance with all standards and requirements of the applicable member jurisdiction, shall not be subject to separate review and approval as a diversion under this paragraph if the generating or receiving pad site is subject to an Approval by Rule issued pursuant to § 806.22(f) and provided all monitoring and reporting requirements applicable to such approval are met.(vi) The diversion of flowback or production fluids, tophole water and captured stormwater from a hydrocarbon development project for which an Approval by Rule has been issued pursuant to § 806.22(f) , to an out-of-basin treatment or disposal facility authorized under separate governmental approval to accept flowback or production fluids, shall not be subject to separate review and approval as a diversion under this paragraph, provided all monitoring and reporting requirements applicable to the Approval by Rule are met and it is handled, transported and stored in compliance with all standards and requirements of the applicable member jurisdiction.(vii) The diversion of any flowback or production fluids, tophole water and captured stormwater from hydrocarbon development projects located outside the basin to an in-basin treatment or disposal facility authorized under separate government approval to accept flowback or production fluids, shall not be subject to separate review and approval as a diversion under this paragraph (a)(3), provided the fluids are handled, transported and stored in compliance with all standards and requirements of the applicable member jurisdiction.(viii) The diversion of drinking water and/or municipal wastewater out of the basin to a municipality on or straddling the basin divide if provided by or through a publicly or privately owned entity and regulated by the appropriate agency of the member jurisdiction shall not be subject to review and approval as a diversion under this paragraph (a)(3) of this section or as a consumptive use under paragraph (a)(1) of this section.(ix) The diversion of drinking water and/or municipal wastewater into the basin to a municipality if provided by or through a publicly or privately owned entity and regulated by the appropriate agency of the member jurisdiction shall not be subject to review and approval as a diversion under this paragraph (a)(3).(4)Crossing state boundaries. Any project on or crossing the boundary between two member states.(5)Significant effect. Any project in a member state having a significant effect on water resources in another member state.(6)Comprehensive plan. Any project which has been or is required to be included by the Commission in its comprehensive plan, or will have a significant effect upon the comprehensive plan.(7)Determination. Any other project so determined by the commissioners or Executive Director pursuant to § 806.5 or 18 CFR part 801. Such project sponsors shall be notified in writing by the Executive Director.(8)Natural gas. Any unconventional natural gas development project in the basin involving a withdrawal, diversion or consumptive use, regardless of the quantity.(9)General permit. Any project subject to coverage under a general permit issued under § 806.17 .(b) Any project that did not require Commission approval prior to January 1, 2007, and undergoing a change of ownership, shall be exempt from the requirements of paragraph (a)(1)(iv), (a)(2)(v), or (a)(3)(iv) of this section if it is a: (1) Transfer of a project to the transferor's spouse or one or more lineal descendents, or any spouse of such lineal descendents, or to a corporation owned or controlled by the transferor, or the transferor's spouse or lineal descendents, or any spouse of such lineal descendents, for so long as the combined ownership interest of the transferor, the transferor's spouse and/or the transferor's lineal descendent(s) and their spouses, continues to be 51 percent or greater; or(2) Transfer of land used primarily for the raising of food, fiber or forage crops, trees, flowers, shrubs, turf products, livestock, or poultry, or for aquaculture, to the extent that, and for so long as, the project's water use continues to be for such agricultural water use purposes. 86 FR 52965 , Sept. 24, 2021 82 FR 29390 , 7/1/2017; 86 FR 52965 , 9/24/2021