Subject to the notice requirements of §§ 157.205(b) and 157.208(c) , the certificate holder is authorized to acquire, construct, modify, replace, and operate natural gas facilities that are used to transport either a mix of synthetic and natural gas or exclusively revaporized liquefied natural gas and that are not "related jurisdictional natural gas facilities" as defined in § 153.2(e) of this chapter. The cost of a project may not exceed the cost limitation provided in column 2 of table 1 to § 157.208(d) . The certificate holder must not segment projects in order to meet this cost limitation.
18 C.F.R. §157.212