An application for license under this subpart must contain the following information in the form specified. As provided in paragraph (f) of this section, the appropriate Federal, state, and local resource agencies must be given the opportunity to comment on the proposed project, prior to filing of the application for license for major project-existing dam. Information from the consultation process must be included in this Exhibit E, as appropriate.
(a)Initial statement.Before the Federal Energy Regulatory Commission
Application for License for Major Project-Existing Dam
(1) (Name of applicant) applies to the Federal Energy Regulatory Commission for a (license or new license, as appropriate) for the (name of project) water power project, as described in the attached exhibits. (Specify any previous FERC project number designation.)(2) The location of the project is: State or territory: _______________________________
County: _______________________________
Township or nearby town: _______________________________
Stream or other body of water: _______________________________
(3) The exact name and business address of the applicant are: _______________________________
_______________________________
_______________________________
The exact name and business address of each person authorized to act as agent for the applicant in this application are:
_______________________________
_______________________________
_______________________________
(4) The applicant is a [citizen of the United States, association of citizens of the United States, domestic corporation, municipality, or state, as appropriate] and (is/is not) claiming preference under section 7(a) of the Federal Power Act. See16 U.S.C. 796 .(5)(i) The statutory or regulatory requirements of the state(s) in which the project would be located that affect the project as proposed, with respect to bed and banks and to the appropriation, diversion, and use of water for power purposes, and with respect to the right to engage in the business of developing, transmitting, and distributing power and in any other business necessary to accomplish the purposes of the license under the Federal Power Act, are: [Provide citation and brief identification of the nature of each requirement; if the applicant is a municipality, the applicant must submit copies of applicable state and local laws or a municipal charter, or, if such laws or documents are not clear, other appropriate legal authority, evidencing that the municipality is competent under such laws to engage in the business of developing, transmitting, utilizing, or distributing power.](ii) The steps which the applicant has taken or plans to take to comply with each of the laws cited above are: (provide brief description for each law).(6) The applicant must provide the name and address of the owner of any existing project facilities. If the dam is federally owned or operated, provide the name of the agency.